On March 16, 2023, New Indy Catawba LLC (New Indy) applied to the Bureau of Air Quality (BAQ) for construction permits to:
- Incorporate the limits and requirements from the Environmental Protection Agency's (EPA) Consent Decree in Civil Case No. 0:21-cv-02053-SAL. This consent decree was approved by and entered into before the U.S. District Court for the District of South Carolina on November 16, 2022.
- Install and operate a new ash handling system. The new ash handling system is being installed as one of the means by which the facility will discontinue the practice of adding solids to the clarifier as required by the EPA’s consent decree.
On March 23, 2023, New Indy Catawba LLC (New Indy) applied to the Bureau of Air Quality (BAQ) for a construction permit to:
- Install and operate a new foul condensate stripper and associated equipment and make changes to existing equipment and the foul condensate treatment scenarios as required by the Consent Order to Correct Undesirable Levels of Air Contaminants. This consent order was signed on November 23, 2022.
BAQ has completed a technical review of the application. The technical review includes reviewing emissions calculations, performing a regulatory review, conducting an ambient air quality analysis and verifying that the proposed project can meet all applicable air quality regulations if constructed and operated in accordance with the air permit applications.
Once the technical review was completed, the three draft air construction permits, draft statements of basis, permit applications, and related documents were placed on public notice from May 13, 2023, through June 20, 2024.
On June 13, 2024, BAQ held a public hearing to accept written and verbal comments on the draft air construction permits for the proposed projects. Below are slides used at the public hearing to summarize the permits and their contents.
On July 22, 2024, BAQ made Department Decisions approving the issuance of the Air Quality Construction Permits to New-Indy. The decisions regarding the air permits were made after careful consideration and complete review of the following: the air permit applications, applicable state and federal air quality regulations, comments made at the public hearing held on June 13, 2024, and all comments received within the public comment period. All public comments received were reviewed and have been included in DES’s permanent record for this facility.
All Permits
Construction Permit CP-50000051
Permit for incorporation of limits and requirements from EPA’s Consent Decree.
- Department Decision
- Construction Permit CP-50000051 v1.0
- Statement of Basis
- March 16, 2023, Application, as amended, for CP-50000051 and CP-50000175
Construction Permit CP-50000061
Permit for installation and operation of a new foul condensate stripper, associated equipment, and foul condensate treatment scenarios.
- Department Decision
- Construction Permit CP-50000061 v1.0
- Statement of Basis
- March 23, 2023, Application, as amended
Construction Permit CP-50000175
Permit for installation and operation of a new ash handling system.